  • Pre-Application Engagement

    January

     

    -

     

    December 2022

    Pre-application engagement with Glasgow City Council
  • Proposal of Application Notices

    May 2022

     

    -

     

    Complete

    Submission of Proposal of Application Notices to Glasgow City Council
  • Engagement Phase 1

    Summer 2022

     

    -

     

    Complete

    Public & Stakeholder Engagement: Gathering thoughts, ideas and aspirations for the future of Buchanan Galleries
  • Design Presentations

    Summer/Autumn 2022

     

    -

     

    Complete

    Presentations to Glasgow Urban Design Panel
  • Engagement Phase 2

    Autumn 2022

     

    -

     

    Complete

    Public & Stakeholder Engagement: Seeking views on the emerging development proposals
  • Engagement Phase 3

    Early 2023

     

    -

     

    Complete

    Public & Stakeholder Engagement: Seeking views on finalised development proposal
  • Submit Planning Applications

    TBC

     

    -

     

    Upcoming

    Submit planning applications for overarching masterplan site (Planning Permission in Principle) and ‘Masterplan Phase 1’ on Buchanan Street (detailed Planning Permission)
  • Targeted Approval

    TBC

     

    -

     

    Upcoming

    Targeted approval of masterplan planning applications
  • First Works Commence

    TBC

     

    -

     

    Upcoming

    First substantive works to commence on site (Phase 1 demolitions and construction works)
  • Completion of Phase 1

    TBC

     

    -

     

    Upcoming

  • Works Commence on Later Phases

    TBC

     

    -

     

    Upcoming

  • Completion of Masterplan Development 

    TBC

     

    -

     

    Upcoming